TriStar Skyline Update

TriStar Skyline Update

The Batten | Shaw team at TriStar Skyline has completed the 2nd floor of this vertical expansion project. This 33,000+ square foot space was partially built above fully functioning operating rooms and cath labs. The construction included pre-manufactured headwalls, sink walls, toilet rooms, and charting stations as well as exterior wall panels. Two (2) new air handlers were installed to service the addition which includes 36 CCU beds. Join us in congratulating this team on completing this major phase of the project. Next up, the Emergency Department expansion due to complete this November.